2027 IBC Fireproofing: What Changed From 2018 to 2027

This guide covers the 2027 IBC fireproofing changes, plus the 2024 International Building Code changes before them, for spray-applied fireproofing (SFRM) and intumescent fireproofing (IFRM). It goes through the changes item by item and gives an edition-by-edition table of section numbers. It also covers the proposals that failed, the fire code side for owners, and which editions apply in the states we serve.

TLDR: The 2027 IBC fireproofing changes are smaller than the rumor mill suggests. The fire-resistance hours in Table 601 haven’t moved since 2018. What did move is where the rules live, so the same section number can point to a different material depending on the edition. The one real design change in 2027 is how far up a tall column needs protection, and nobody in our territory has adopted it yet.


Say a GC has a spec that reads “special inspection per IBC Section 1705.15.” On a job under the 2018 IBC, that section covers mastic and intumescent coatings. On a job under the 2021 or 2024 IBC, the same number covers spray-applied fireproofing. Cite the wrong edition and the statement of special inspections can leave a material off. That gap shows up at the worst time, when the ceilings are closing and the building official asks for reports nobody planned on.

I’ve been doing this for over forty years. Right now almost every bid request we get is still on the 2021 or 2024 IBC, and none of the states we work in has adopted 2027 yet. The fire ratings in Table 601 didn’t change between those editions, but some of the section numbers did. If you’re reusing a spec from an older job, check which edition the city is on before you copy the section numbers over.

Code note: section numbers on this page are tagged to the IBC or IFC edition they come from. The 2027 International Codes are published, but we couldn’t open the 2027 text for this article. The 2027 items are described from ICC’s hearing results and committee reports and aren’t quoted from the printed book. Code adoption is state and local, so confirm the adopted edition and any local amendments with your authority having jurisdiction.

What Are the 2027 IBC Fireproofing Changes?

The 2027 IBC fireproofing changes come down to one design rule and a few procedures. A new exception to Section 704.2 lets columns under a qualifying tall roof be protected for only their first 20 feet. SFRM special inspection under Section 1705.15 also points to the manufacturer’s installation instructions, and concrete framing becomes restrained by default. Table 601 hours didn’t change.

ICC lists the 2027 IBC first printing as September 2026. Each fireproofing proposal went through ICC’s committee hearings and then the April 2026 public comment hearing in Hartford. The column change, G123-25, survived a challenge at that hearing, as shown in ICC’s 2026 Public Comment Hearing results. ICC confirmed final action results in July 2026.

No state or city in our nine-state territory has adopted the 2027 IBC. For now, the 2027 changes are only a design question for jurisdictions that adopt the code later.

Edition by Edition: Where the Fireproofing Sections Live

The table below tracks the fireproofing sections a GC, architect or inspector cites most, across four IBC editions. The 2027 column reflects ICC’s approved proposals, so check the numbering against the printed 2027 code.

Item2018 IBC2021 IBC2024 IBC2027 IBC
SFRM special inspection1705.141705.151705.151705.15, now also based on the manufacturer’s installation instructions
Intumescent (IFRM) special inspection1705.15 (mastic and intumescent coatings)1705.161705.161705.16, no change, AWCI 12-B stays
Column protection704.2704.2Merged into 704.2704.2, new Exception 4 for columns
Primary frame other than columns704.3704.3704.2 (whole primary frame)704.2
Supporting-construction rule704.1704.1704.1.1704.1.1
SFRM installation requirements704.13704.13704.12704.12, no change found
Table 601 footnote b, 20 foot roof ruleMeasured above any floorMeasured above any floorAbove any floor or mezzanineSame rule, with columns handled by 704.2 Exception 4
Restrained classification703.2.3703.2.1.3703.2.1.3703.2.1.3, concrete restrained by default

Read the first two rows together. Section 1705.15 means intumescent in the 2018 IBC and SFRM in every edition since. A spec should name the edition and the material in the same line.

What Changed in the 2024 IBC for Fireproofing?

The 2024 IBC fireproofing changes are mostly a reorganization of Section 704. The hours, the special inspection numbers and the test standards stayed where the 2021 edition put them. Three changes matter on the job:

  1. Columns and the rest of the primary frame now share Section 704.2. The 2021 IBC had a column section (704.2) and a separate section for primary frame members other than columns (704.3). The 2024 edition deleted the separate column section. Section 704.2 now covers the whole primary structural frame, and 704.3 covers secondary members.
  2. The supporting-construction rule got its own number. The rule that a member’s rating can’t be less than the rating of the construction it supports used to sit in 704.1. The 2024 IBC moved it to 704.1.1.
  3. Footnote b to Table 601 added mezzanines. The roof exemption applies where every part of the roof construction is 20 feet or more above “any floor or mezzanine immediately below.” Before 2024 it read “any floor.”

The renumbering shifted later sections too. The SFRM installation section moved from 704.13 to 704.12, so a spec written with 2021 numbers will cite sections that mean something else on a 2024 job.

The 2027 Column Change: Protection for the First 20 Feet

The biggest 2027 IBC fireproofing change is new Exception 4 to Section 704.2. ICC’s committee approved it at its second hearing on G123-25, and the April 2026 public comment hearing upheld it. As printed in ICC’s Group B committee action hearing report, the exception covers “Columns that are provided with protection for the first 20 feet (6096 mm) above any floor or mezzanine in accordance with IBC Table 601 footnote b.”

Through the 2024 IBC, the footnote b roof exemption never covered columns. A column under a tall roof needed protection for its full height. Under the 2027 text, a column under a roof that qualifies for footnote b only needs protection for its first 20 feet.

The footnote b conditions still apply. Every part of the roof construction has to be 20 feet or more above any floor or mezzanine immediately below. The exemption still excludes Groups F-1, H, M and S-1, which covers most factories, warehouses and big-box stores. The National Fireproofing Contractors Association opposed G123-25 and has listed reversing it as a goal for the next code cycle.

Say an architect is laying out a school gymnasium in Type IIA construction, with every part of the roof 26 feet above the floor. Table 601 puts the primary frame at 1 hour. Under the 2024 IBC, footnote b lets the roof joists and deck go bare, but the columns still get protected to the top. Under the 2027 IBC, those columns would need protection for the first 20 feet and could stop there. That leaves about 6 feet of each column unprotected, and it adds up across every column in the room.

Until the AHJ adopts the 2027 IBC, the column goes full height, and the protection still follows the listed design.

Other 2027 IBC Fireproofing Changes Worth Knowing

Four more approved items touch fireproofing work. None of them changes a rating.

  • SFRM inspection follows the manufacturer’s instructions (S3-24). Section 1705.15 adds the manufacturer’s installation instructions to the basis for special inspection, next to the approved fire-resistance design. The committee approved it 12 to 0 at the first hearing. No one challenged it, and it went through on the consent agenda. Per ICC’s hearing results it should be in the 2027 IBC, but confirm the exact sentence in the printed code. NFCA’s reason was that surface preparation, temperature and ventilation are spelled out in the instructions, and the listing doesn’t cover them.
  • Concrete framing is restrained by default (FS2-24). Section 703.2.1.3 gets an exception. Concrete girders, beams and slabs connected to concrete framing or walls per ACI 318 count as restrained, unless the licensed architect or engineer of record determines otherwise. Steel stays unrestrained unless shown otherwise. An AISC comment to add steel failed.
  • Calculated SFRM and intumescent thickness (FS85-24). Section 722 now lets steel fire resistance be designed by AISC 360 Appendix 4. That opens a path to calculated thickness. Advanced analysis goes through the code’s alternative design provisions in Section 104.2.3.
  • Extending test results (FS3-24). Section 703.2.2 lets ASTM E119 or UL 263 results be extended using ASTM E2032 principles.

For a GC, S3-24 is the one that matters in practice. The special inspector can cite the manufacturer’s application conditions as well as the UL design. Our crews already apply every product to those instructions.

What Stayed the Same and What Failed in 2027

Table 601 hour values didn’t change in 2024 or in 2027. Seven proposals touched Table 601 in the 2027 cycle, and every one that would have changed an hour value failed.

Unchanged in 2027:

  • Intumescent inspection. Section 1705.16 still uses AWCI 12-B, the industry procedure for checking intumescent thickness.
  • SFRM sampling and acceptance. Thickness, density and bond strength sampling under Section 1705.15 carry over. Bond strength is still tested to ASTM E736, with 150 psf as the Section 1705.15.6 minimum. High-rise buildings follow the higher values in Table 403.2.3.
  • The high-rise bond strength table (Table 403.2.3). No proposal touched it.

Failed in 2027:

  • Occupiable roofs (G119, G120, G121-25). Proposals to limit footnote b where a roof is occupiable were disapproved.
  • ASTM inspection standards (S2, S4, S5-24). Proposals to replace the SFRM rules with a new ASTM practice, add a board-and-wrap inspection section and drop AWCI 12-B were disapproved at every hearing.
  • Parking garage ratings (G66-25, G116-25). Proposals to raise fire-resistance in parking garages didn’t pass. G116-25 was withdrawn at the April hearing.
  • Secondary attachments (FS10-24). NFCA’s proposal to protect more of the secondary attachments to steel was disapproved at committee and withdrawn at the April hearing. The existing rule stays.

The Fire Code Side: IFC 701.6, 708.1 and the New 708.2

The IBC covers how fireproofing goes on. Once the building opens, the International Fire Code makes the owner responsible for keeping it there.

IFC 701.6, owner’s responsibility (2021 and 2024 IFC). The owner keeps an inventory of required fire-resistance-rated construction. That construction “shall be visually inspected by the owner annually” and has to be repaired where damaged, altered, breached or penetrated. Concealed elements are exempt unless the space opens by moving a panel, access door or ceiling tile. No 2027 proposal changed 701.6.

IFC 708.1, since the 2021 IFC. Section 708 was new in the 2021 IFC. It requires SFRM and intumescent, where they were required when the building was permitted, to be visually inspected for exposed substrate. It doesn’t set a frequency of its own. NFCA reads it together with the annual 701.6 inspection.

What the 2027 IFC adds. Per ICC’s hearing results, three NFCA proposals passed:

  • F91-24 extends 708.1 to “other materials used to provide fire-resistance protection,” meaning boards and wraps.
  • F89-24 changes “resistant” to “resistive” to match the IBC.
  • F90-24 adds Section 708.2 on repair. Protection has to be securely bonded, with no delamination, cracks or voids exposing the substrate. Where the original material and listing are known, repairs follow that listing and the manufacturer’s repair instructions. Where they aren’t, repairs use the same material type and thickness.

We couldn’t get the 2027 IFC text to quote, so this section is based on ICC’s approved proposals. Check it against the printed page.

Who Uses NFPA 1 or NFPA 101 Instead of the IFC?

Several states and the federal Medicare program use NFPA codes instead of the IFC.

  • Nebraska. The state fire code is NFPA 1 and NFPA 101, 2012 editions, by statute.
  • Wisconsin. The state fire code for public buildings and places of employment is NFPA 1, 2012 edition.
  • Texas state buildings. The State Fire Marshal inspects state-owned and state-leased buildings to NFPA 1 and NFPA 101, 2021 editions. Texas cities adopt their own fire codes.
  • Healthcare under CMS. Hospitals in Medicare and Medicaid follow NFPA 101, 2012 edition, under 42 CFR 482.41. Iowa also adopts the 2012 NFPA 101 for health care.

NFPA 1 Section 12.3.3 requires all fire-resistive construction to be maintained. The 2021 edition, as cited by Montgomery County, Maryland, calls for a visual inspection in high-rises at least every three years where readily accessible. NFPA 101 sets no fixed frequency for fire-resistive construction. It defers to its other chapters or the AHJ.

Which IBC and IFC Editions Apply in Our States?

None of the nine states we serve has adopted the 2027 IBC or IFC. The editions in force today run from the 2018 IBC to the 2024 IBC, and several cities set their own. Our service areas page lists the states and cities we work in.

JurisdictionBuilding codeNotes
Oklahoma (statewide)2024 IBC, effective Sept 14, 2026Skipped the 2021. 2024 IFC same date
Iowa (state building code)2024 IBC2024 IFC with amendments
Phoenix, Arizona2024 IBC, effective Aug 1, 2025City code
Tucson, Arizona2024 IBC, effective Jan 1, 2026City code
Wichita-Sedgwick County, Kansas2024 IBCLocal adoption
Johnson County, Kansas2024 IBC, effective Jan 1, 2027Cities inside the county adopt their own
Wisconsin (commercial)2021 IBC since Sept 1, 2025NFPA 1 2012 fire code
Lincoln, Nebraska2021 IBCLocal amendments
Nebraska (statewide)2018 IBCNFPA 1 and 101, 2012
Minnesota2018 IBC base2024 IBC in rulemaking, no effective date
Kansas City, Missouri2018 IBC baseMissouri has no statewide fire code

Texas is set city by city. Dallas and Fort Worth enforce the 2021 IBC. The state fire codes split further. Kansas’s statewide fire code is still the 2006 IFC, and the state fire codes in Arizona and Minnesota are based on the 2018 IFC. All three model editions came before IFC Section 708, so the 708.1 check of fireproofing isn’t in those state codes unless they amended it in.

So a GC running a Minnesota job and an Iowa job in the same month carries two sets of section numbers. SFRM inspection is 1705.14 on the Minnesota job and 1705.15 on the Iowa job.

FAQ

Has any state adopted the 2027 IBC fireproofing provisions? Not in our territory. As of November 2026, none of Texas, Oklahoma, Kansas, Nebraska, Minnesota, Wisconsin, Arizona, Missouri or Iowa has adopted the 2027 IBC or IFC. Adoption usually trails publication by a year or more, so check with your AHJ before you design to them.

Does the 2027 IBC change the hours in Table 601? No. Every proposal that would have changed an hour value in Table 601 failed in the 2027 cycle, so the ratings by construction type carry over from the 2024 edition.

Do columns under a 20 foot roof still need full-height fireproofing? Through the 2024 IBC, yes. Footnote b never covered columns. Under the 2027 IBC, Section 704.2 Exception 4 lets those columns be protected for the first 20 feet above any floor or mezzanine. The footnote b conditions and the F-1, H, M and S-1 exclusion still apply.

Is SFRM special inspection 1705.14 or 1705.15? It depends on the edition. The 2018 IBC puts SFRM at 1705.14 and intumescent at 1705.15. The 2021, 2024 and 2027 editions put SFRM at 1705.15 and intumescent at 1705.16. Minnesota and Nebraska statewide are still on 2018 numbers.

Did the 2027 IBC replace AWCI 12-B for intumescent inspection? No. The proposal to swap AWCI 12-B for an ASTM standard was disapproved, so Section 1705.16 still calls for it.

Who inspects fireproofing after the building opens? Under the 2021 and 2024 IFC, the owner visually inspects required fire-resistance-rated construction annually (Section 701.6), and Section 708.1 adds a check for exposed substrate on SFRM and intumescent. Buildings under NFPA 1 or NFPA 101 follow those codes and the AHJ. We apply fireproofing and don’t inspect our own work.

Key Takeaways

  • Ratings held steady
    Table 601 hours did not change in 2024 or 2027.
  • Numbers moved
    SFRM inspection: 1705.14 in 2018, 1705.15 since 2021.
    Intumescent inspection: 1705.15 in 2018, 1705.16 since 2021.
  • 2024 reorganized Section 704
    Columns and the primary frame merged into 704.2.
    Supporting construction moved to 704.1.1.
    Footnote b added mezzanines.
  • 2027 changed columns
    704.2 Exception 4: first 20 feet of column protection under a qualifying roof.
    Applies only where a jurisdiction adopts 2027, and F-1, H, M and S-1 are still excluded.
  • 2027 procedural changes
    SFRM inspection also follows the manufacturer’s installation instructions.
  • The fire code covers the owner
    IFC 701.6 calls for an annual visual inspection, and IFC 708.1 has applied since 2021.
    2027 IFC adds other materials and 708.2 repair rules.
    Nebraska, Wisconsin, Texas state buildings and CMS healthcare use NFPA codes instead.

Related Reading

If you want fireproofing applied by a crew that reads the edition on the permit and protects every column to the height your adopted code requires, that’s the work we do. Bahl Fireproofing is NFCA accredited for SFRM and IFRM. Your independent special inspector, not us, verifies the result. We work throughout Texas, Oklahoma, Kansas, Nebraska, Minnesota, Wisconsin, Arizona, Missouri, and Iowa. See our spray-applied fireproofing services, call me at 512-387-2111, email ross@bahlfireproofing.com, or Contact Bahl Fireproofing to go over your drawings.


This article gives general educational information about building and fire code changes for fireproofing. It isn’t engineering, legal or code-compliance advice, and it doesn’t replace project-specific direction from a licensed architect or engineer. Code citations refer to specific IBC, IFC and NFPA editions, and adopted editions and local amendments vary by jurisdiction. The 2027 items are described from ICC’s hearing results, so confirm the exact wording in the printed 2027 code. Fire-resistance ratings depend on the tested and listed assembly and correct installation, so confirm them against the applicable UL design. Inspection requirements are set by the authority having jurisdiction and the project’s approved documents.

Ross Bahl, owner of Bahl Fireproofing
Written for Bahl FireproofingRoss Bahl, Owner

Ross owns Bahl Fireproofing, the commercial fireproofing and insulation subcontractor his family started in 1977. Every code figure on this site is checked against the published source before it goes up. More about Ross.

On this page
Bidding this scope?Send us the drawings.

Spray-applied fireproofing, intumescent coatings, K-13, spray foam and Core Foam, self-performed across nine states. We price the assembly on your drawings, not a square-foot guess.

Request a bidCall the office512-387-2111

Have a rated assembly to cover?

Send the drawings and the spec section. We come back with the scope in and the scope out stated plainly, so your bid tab compares the same work across every subcontractor on it.

Call the office512-387-2111Request a bid